ACHIEVEMENT
Achievement Update
Berth Development
  • 40 Number of Berths
  • Total Berth length of 10,000 m

Breakwater Dredging and Reclamation
  • 12,000 m of Breakwater
  • Over 270 Million Cum
  • Reclamation in 2500 ha area

Container Terminal
  • 4 Container Terminals with Total Capacity of 5.1 Million TEU per annum
  • Length of Berths - 2700 m

Single Point Mooring
  • Offshore Crude Handling System for handling of VLCC vessels

Major Equipment at Berth
  • 51 Nos (RMQC – 16, Ship unloaders – 7, MHC – 28)

Major Equipment at Yard
  • 63 Nos (RTG – 42, Stacker/Reclaimer - 14, Goliath – 7 )

Conveyors
  • Total Conveyor Length of 52,000 m

Storage Area Development
  • Closed Storage Area Development of 400,000sq m
  • Liquid Tank farm Development of 700,000 KL
  • Open Storage Area Development of 1,500,000sq m

Building and Structures
  • Industrial Structure, Substation, Office, Hospital, School, Township, Auditorium, Gymnasium, Workshop, Stores, Water tank, Pump house
  • Total area Development of 1,000,000 Sq Ft

Desalination Plant
  • 50 MLD Desalination Plant

Road
  • 200 km of Roadway infrastructure

Railway
  • 300 km of Railway infrastructure

Airport
Private airport at Mundra with 2000 m long runway

Water Pipeline
  • 200 Km

Transmission Lines
  • Total Length of 60,000 m

Silo
  • Total silos with capacity of 30,000 MT

Substations
  • AIS substations: 220 kV / 66 kV, 3 nos. GIS substations: 66 kV, 3 nos.